country route of desert and mountain - one of the longest and largest overland gas pipelines in the The United Arab Emirates (UAE). It is designed to carry significant quantities of Dolphin gas via Taweelah directly to the UAE east coast. Dolphin Energy has been working with contractor PJSC Stroytransgaz on the construction of the pipeline. Although it experienced some construction delays in the early phases of development, the project is on track to be completed by the third quarter of 2010. The next major completion milestone for TFP is scheduled for February 2010. This will mark the completion of approximately 127 kilometres of pipeline that extends from Dolphin's Taweelah Facility and ties in with Dolphin's existing Al Ain to Fujairah pipeline. This will then direct quantities of gas to the new power station in Fujairah until final completion of the new TFP pipeline.